SEABROOK UNIT 2 MAY BE HALTED
The lead participant in the Seabrook nuclear power project in New Hampshire bowed to intense pressure from the other owners yesterday and said it would agree, under certain conditions, to cancel the second Seabrook reactor. This move by the Public Service Company of New Hampshire appeared to clear the way to scrap Unit 2, a 1,150-megawatt facility that is 23 percent complete and has already cost a consortium of 16 New England utilities about $2.5 billion. Public Service owns 35.6 percent of the project, and until yesterday it had consistently vetoed efforts by the other owners - particularly utilities in Massachusetts, Maine and Connecticut - to cancel the project. No Change in Basic Stand Dallas Hamerlinck, vice president for public affairs of Public Service, said the company's position favoring completion ''hasn't changed.'' But he added, ''You sometimes get to a point when you can't go on.''